Norstead collapsed owing £7m

Norstead collapsed owing £7m

Newcastle-based Norstead collapsed owing £7.2m to unsecured creditors, administrator FRP Advisory has revealed.

The mechanical & engineering specialist contractor, which turned over £20.3m in 2021, was forced to make 52 staff redundant before entering administration at the end of February. The group was the sister company of Metnor Construction, which also collapsed earlier this year, owing £10m.

Now a statement of affairs published by FRP Advisory shows that Norstead’s net liabilities are £13m, with the group also owing £6m to its shareholders, £88,000 to employees and £50,000 to HMRC.

The group had £641,000 in the bank at the time of its collapse, with the sale of its vehicles likely to raise another £181,000.

The group’s unsecured creditors include dozens of suppliers and subcontractors, which are owed tens, and in some cases hundreds, of thousands of pounds. The biggest outstanding debt is to Metnor, which is owed £885,000, closely followed by Accredited Insurance, owed £870,000.

Other companies owed money include manufacturers Northern Vent Services (£54,000), Ventilux UK (£69,000), Prefabricated Solutions Limited (£136,000) and Frenger Systems (£45,000), as well as pipework installers Truarc (£58,000).

FRP Advisory said Norstead collapsed due to increased labour and material costs, Covid-related costs, the withdrawal of a key funder and a lack of value that would have been created through novating its contracts.