Cost of Morgan Sindall’s Old Street roundabout project rises by £20m

Cost of Morgan Sindall’s Old Street roundabout project rises by £20m

old-street-new-entrance.jpg

CGI of the new entrance to Old Street Station

The cost of the Morgan Sindall-led overhaul of Old Street Station and roundabout in east London has risen by £20m.

A freedom of information (FoI) request submitted by Construction News’ sister magazine New Civil Engineer has revealed that the project has cost over £103m to date and is expected to top £132m by the time it completes in early 2024.

The Transport for London (TfL) project was originally forecast to complete in 2020 and the most recent cost estimate was £112m. The upgrade will see the station entrances modernised and the 1960s roundabout rearranged to create a safer environment.

A breakdown of the costs incurred on the project so far (see below) and the projected final costs show that £70.1m has been spent on main construction works, which are due to cost £88.3m in total.

The new main entrance will have a green roof, with new lifts also being installed. The north-west leg of the roundabout has been permanently closed to all traffic and work is continuing to create a major new public space with better walking and cycling access to Old Street Station.

TfL said that the work had been impacted by the pandemic, which saw the site shut down for three months. This was followed by months of social distancing measures, which made working on a confined site difficult.

The scope of the work has also increased significantly. During the excavation for the project, previously unrecorded utilities infrastructure was discovered and had to be removed.

The station’s mechanical & engineering systems are also complex and have caused delays to the works on the new entrances, with existing 1960s systems needing to be redesigned and replaced.

The costs include a £7.2m contingency for risks on the project. A TfL spokesperson said: “The allowance of £7.2m is to cover for any identified risks materialising on the project which could cause further delay or disruption and impact on the completion date and associated costs. The estimated final costs may be lower if the risk share is not utilised.”

Cost category Cost to date (£m) Estimated final cost (£m)
Project management and engineering 9.00 10.66
Design 11.50 12.08
Third-party stakeholders and utility providers 9.08 9.17
Surveys and enabling works 3.80 4.85
Construction 70.10 88.33
Risk 0.00 7.20
Total 103.48 132.29

What has been done on the project so far

  • Refurbishment of the pedestrian crossing on Old Street east.
  • Removal of the existing roundabout and permanent closure of the north-west leg to create a new public space
  • Road traffic movements to a two-way system.
  • Opening of a new Cowper Street station entrance.
  • Refurbishment and reopening of the City Road (north) exit stair (north-west exit) with the green line towards Moorfields Eye Hospital reinstated.
  • Closure of the ramp of City Road (north) exit (nort-hwest exit) to begin works on the new lift.
  • Permanent closure of subway 1 (north-east exit) and opening of a new section of segregated cycle lane between City Road (north) and Old Street east.
  • Opening of a section of new segregated cycle lane between Old Street east and City Road south.
  • Installation of two new passenger lifts ahead of testing this summer.